Tips, notifications
Use
Project profile specify almost all important characters,
profiles, parameters for the project. It is also a meanningful
index of PS module.
Notice
Many profiles and parameters, such as costing sheet,
network profile, settlement profile etc. , are not assigned during
this phase due to not been defined. In the process below will be
defined and assigned.
Create another project profile V for internal construction
project in the same way. Differences are that V can has many
roots and the project type is V.
3.2.5 Specify persons responsible for WBSE OPS6
3.2.6 Define field selection for WBS OPUJ/ OPUK
The field selection for Project Definition is defined as
Tips, notifications
Use
The definition here can not be conflicted whit the parameters
has been maintained in Project profile.
The same rules will be effect when you define fields
selection for WBS element, network, orders or etc.
Settings
Default setting is input, and u can change that status to
req, disp or hide.